This room (formerly known as the VI) will be one of our brand-new EEG labs. Once completed, it will provide a dedicated, purpose-built space for conducting EEG research with both adult and infant participants. Below you can follow the progress of the construction from start to finish!
Construction progress
12 mar
Last update Now

Connections for the pantry tap and electricity installed (2).
9 mar

Connections for the pantry tap and electricity installed (1).
23 feb

Foam and cabin floor installed (it’s going fast!)

Wall is being painted and cabin floor preparations continue.
17 feb

Floor preparation for cabin. The floors have to be fortified to enable them to carry the weight of the sound-attenuated booths.
3 feb

Wood covering the holes that were made in the floor to prepare them for fortification.
Jan 2026
Start renovation
Phase 1

Dusk in the EEG lab.

Floor removed! The floors have to be fortified to enable them to carry the weight of the sound-attenuated booths.