Institute for Language Sciences Labs

Room 1.04, Head-Turn-Preference cabine & Washing room

This room will be our brand-new washing room where participants can wash their hair after participating in an EEG experiment. Once completed, more than half the room will occupy the head-turn-preference cabin and the rest of the space will be the washing room. Below you can follow the progress of the construction from start to finish!

Construction progress



13 mar
Last update Now


13 mar 1


13 mar 2

Entrance HTP cabin.


13 mar 3

Floor and walls of HTP cabin installed.



12 mar


12 mar 1

Floor HTP cabin being prepared.



10 mar


10 mar 1



9 mar


9 mar 1

HTP cabin material.


9 mar 2


9 mar 3

View from above: HTP cabin material.


9 mar 4

Connections for the washbasin tap installed.



3 mar


3 mar 1

Washing room wall placed.placed



2 mar


2 mar 1

Washing room wall placed


2 mar 2

Inside of washing room



27 feb


27 feb 1

Washing room wall frame placed.


27 feb 2

Opening for the door into the HTP booth looking good, concrete flooring has dried.


27 feb 3

The new labs will have daylight!


27 feb 4

Wooden wall frame separating the HTP booth from the participant post-EEG washing room.



26 feb


26 feb 1

Dusk in the new HTP lab.



23 feb


23 feb 1

Concrete flooring has been put in and is drying.



17 feb


17 feb 1

Floor being removed. The floors have to be fortified to enable them to carry the weight of the sound-attenuated booths.



12 feb


12 feb 1

Interesting machine for the floor removal.



3 feb


3 feb 1

This is the view from the washing room. You can see the future HTP experimenter room on the other side.



Jan 2026
Start construction
Phase 1


jan 2026 1

Outline and small hole for the door made and floor removed! The floors have to be fortified to enable them to carry the weight of the sound-attenuated booths.