This room will be our brand-new phonetics lab (with three booths). Once completed, it will provide a dedicated, purpose-built space for conducting speech research and behavioral experiments, as well as stimulus recording. Below you can follow the progress of the construction from start to finish!
Construction progress
13 mar
Last update Now

Air-handling system cabin being installed.
10 mar

Walls second and third cabins placed.
5 mar

Preparation floors second and third cabins

First cabin placed!
26 feb

Wall being painted.
23 feb

Other side of the lab, with concrete drying where the sound-attenuated booths will be.
17 feb

Floor preparation for cabin.
3 feb

Holes in the floor covered with wood. The floors have to be fortified to enable them to carry the weight of the sound-attenuated booths, and this involves opening them up first.
Jan 2026
Start construction
Phase 1

You can see the historic ceiling using reed for insulation.